Solar Guidelines and Application

 

UPDATE: WE ARE CURRENTLY STILL ACCEPTING SOLAR APPLICATIONS TO QUALIFY FOR OUR EXISTING NET ENERGY METERING TARIFF UNTIL FURTHER NOTICE.

 

Application Process:

1. Submit application, net metering agreement, interconnection agreement, a single line diagram, net metering equipment specifications sheet, and a copy of the system contract and/or sales proposal.  A $600 application fee will also be required.

2. MID will review the application packet.

3. A pre-construction meeting will be scheduled on site prior to the system installation.

4.  MID will issue approval to move forward with construction upon completion of the meeting if all other requirements are satisfied.

5. MID will perform the MID PV inspection (after the City/County Code inspection).

6. MID will have meter placed for new PV system.

7. MID will establish a customer-generator electric utility account pursuant to the Photovoltaic Interconnection Agreement and issue Permission to Operate (PTO) to the customer.

You can access and download the Photovoltaic System Application  HERE.

 


QUESTIONS:

Customer Programs Manager
P.O. Box 2288, Merced, CA  95344-2288
PHONE:   (209) 354-2819
FAX:  (209) 726-7010
E-MAIL:  rebates@mercedid.org

©2018 Default | Technical contact: helpdesk@mercedid.org | Privacy Policy